Balal region is located in about 20 Km from C-7 platform in South Pars borderline. The goal of defining this project is to complete the feed to SP12 refinary.
Type: GC

The project is implemented on GC basis and is outlined as follows:

  • Responsibility of leadership, management and integrating agreement and preparation of sub-tenders documents as well as conducting reservoir and surface studies and drilling design (notified through letter no. 2062-3349 dated June 2, 2018)
  • Construction of a four-pod jack under design and items available in 12D Phase platform on EPCI basis
  • Conducting EPD tenders for drilling an appraisal well, a learning well and six development wells for production of five hundred million cubic feet gas per day
  • Conducting EPC tenders for offshore installation, including wellhead deck (five hundred million cubic feet gas per day) and marine pipeline (20.4 inch) to the SPD12C platform for 22 Km together with optical fiber cable and network

Picture


Established in 1998, Petropars Ltd. (PPL) was founded in order to contribute towards the development of Iran’s vast energy resources PPL specializes as a developer of exploration exploitation and production in upstream projects... Read more