FA

NEWS & Articles of Petropars

Successful Completion of Pre-Commissioning and Hydrostatic Operations of the First Offshore Pipelin

  Successful Completion of Pre-Commissioning and Hydrostatic Operations of the First Offshore Pipelin

Successful Completion of Pre-Commissioning and Hydrostatic Operations of the First Offshore Pipelin...

 

The Pre-Commissioning operations of 32” and 4.5” pipelines of SPD12C Jacket including Spool Pieces, Free Span Correction, Pigging and hydrotests were completed on Khordad 25, 1391(June 14,2012) by IOEC and IOEC-affiliated contractors. 

Upon erection of SPD12C Jacket, the 32”pipeline will transfer to Phase 12 onshore facilities one billion cubic feet of the gas produced in Phase 12.

 

Pictures
Share

Established in 1998, Petropars Ltd. (PPL) was founded in order to contribute towards the development of Iran’s vast energy resources PPL specializes as a developer of exploration exploitation and production in upstream projects... Read more