POSCO Projects

SPD19

  SPD19

Phase 19 Project as one of the south pars phases in the west part and at the borderline south pars phase was modified to produce 2000 MMSCFD. The Phase 19 Drilling Project consisted of 3 areas of operation A,B and C with 19 wells all of which have been drilled and handed over POGC.
Row SPD19 original wells "+/-" by client Remained Wells comp.
1 Platform A 5 0 5 5
2 Platform B 5 0 5 5
3 Platform C 5 0 5 5
4 Total 15 0 15 15