Our Projects South Pars Phase 12 Latest Status
 
  
Latest Status

The overall actual project progress is 6.61%. The status of the project by July 31, 2008 is as following:
1. Pre Project Studies and Basic Engineering

  • Following basic designs and studies has been completed:
    • Onshore and Offshore Basic Design / FEED by WorleParsons
    • Offshore Survey by Horizon
    • Onshore Topographical Survey by Atlas Tehran
    • Onshore Geotechnical Investigation by Zamiran
    • Basic design of Sulphur Recovery Licensed Unit by WorleyParsons
    • Basic design of Gas Sweetening Licensed Unit by Prosernat
    • Flare Substructure and Coastal Protection Basic Design by Daryabandar
    • Drainage System Design for Onshore Gas Plant by Abfan
    • Accommodation Camps and Offices basic Design by RahShahr
    • Basic Design for NIOC Operating Base by Daryabandar
    • Field Measurement and Modeling for NIOC Operating Base by Darya Negar Pars
    • Review and Approval of Basic Design for NIOC Operating Base by Alive Vof
  • Following study is ongoing:
    • 3D Seismic Data Processing & Interpretation
    • Consultants:   CADCAM and Paradigm
    • Commencement Date: November 27, 2006
    • Progress :     99.48% 

2.Onshore Facilities

  • Gas Plant Main Site Preparation EPC
    • Contractors:  
      • Abad Rahan Pars
      • Fater Kousaran Jonoob (The contract has been terminated)
      • Karan Darya (Implementation of Coastal Protection as Additional Work)
    • Overall Progress:   94.26%

 

 

 

 

 

 

 

  • Accommodation Camps and Offices Site Preparation:
    • Contractor:   Abad Rahan Pars
    • Commencement Date:   December 4, 2007
    • Progress:     88.48%

 

 

 

 

 

 

     

  • Gas Plant Flood Protection Channel:
    • Contractor:   Abad Rahan Pars
    • Commencement Date:   December 4, 2007
    • Progress:     19.09%
  • Gas Plant Flare Substructure EPC
    • Contractor:   Karan Darya
    • Commencement Date:   December 11, 2007
    • Progress:    28.69%

 

 

 

 

 

 

 

  • Gas Plant EPC1, Tanks And Non-Industrial Buildings EPC Contract
    • Contractor:   NASR Consortium
    • Commencement Date:   May 14, 2008
    • Progress:    3.38%

  •  Gas Plant, Liquid Processing And Utilities EPC Contract (EPC2)
    • Issued TBE report and ongoing commercial bid evaluation for Onshore Gas Plant EPC2 tender
    • Forecast award date of the contract will be mid September 2008
  • Gas Plant, Gas Processing EPC Contract (EPC3)
    • Ongoing technical bid evaluation for Onshore Gas Plant EPC3 tender
    • Forecast award date of the contract will be late October 2008
  • Gas Plant Long Lead Items
    • Signed contract with OTC/Siemens for supply of Off Gas and Refrigerant Compressors as Gas Plant LLIs
    • Concluded the tender for Nitrogen Generation Package
    • Bid closing date for Manual and Shutdown Valves greater than 32"
    • Ongoing tender evaluations for the rest

 3. Offshore Facilities

  • Wellhead Platform Jackets EPCI
    • Contractor:                   ISOICO
    • Commencement Date:    January 8, 2007
    •  Progress:                    59.25%

 

 

 

 

 

  • Topsides and Ancillaries EPCI
    • Contractor:   IOEC
    • Commencement Date:  January 10, 2008
    • Progress:    0.7%
  • Sealines and SPM & Condensate Export Facilities EPCI
    • Contractor:   IOEC
    • Commencement Date:  October 15, 2007
    • Progress:    16.41% 

 4. Wells

  • Tendering and Management
    • Signed the contracts for supply of drilling tubular, Wellhead & X-mas Tree, Down Hole Completion & Liner Hanger Equipment and drilling Jack-up Rig
    • Held 17 tenders by Auxiliary Transaction Committee for urgent drilling needs
    • Finalized tender for drilling Mud Line Suspension and Surface Wellhead contract
    • Ongoing technical bid evaluation for drilling Integrated Technical Services
    • Tender for materials to supply of drilling 26" conductor is being concluded
  • Appraisal Well Drilling
    • Start Appraisal Well drilling on June 26, 2008, drilled 2185m by end of July 2008
    • Actual progress of operation up to end of July is 17.04% vs 19.97% plan
    • 36'', 26" and 17 ½" sections drilled and completed
    • Ongoing drilling on section 12 ¼"
  • Supply of Materials, Equipment and Services
    • Delivery of Tubular for PO No.1 to the warehouse in Kish by SUMITOMO
    • Most of required materials for appraisal well are borrowed from POGC and PEDCO and all of them run in well up to this section successfully
    • Received part of the FZE ordered materials to warehouse in Kish and some of the others finalized and scheduled for delivery

5. NIOC Operating Base

  • NIOC Operating Base EPC:
    • Issued TBE report and ongoing commercial bid evaluation
    • Held tender for geophysical study of the step-like feature in the south of NIOC OPBS port
    • Following up the NIOC Operating Base permissions from EPO & PSO
    • Submission of technical and commercial clarifications to bidders
    • Forecast award date of the contract will be in September 2008
 Print   