Our Projects South Pars Phase 12 Latest Status
|
|
| |
|
 |
|
|
|
The overall actual project progress is 6.61%. The status of the project by July 31, 2008 is as following:
1. Pre Project Studies and Basic Engineering
- Following basic designs and studies has been completed:
- Onshore and Offshore Basic Design / FEED by WorleParsons
- Offshore Survey by Horizon
- Onshore Topographical Survey by Atlas Tehran
- Onshore Geotechnical Investigation by Zamiran
- Basic design of Sulphur Recovery Licensed Unit by WorleyParsons
- Basic design of Gas Sweetening Licensed Unit by Prosernat
- Flare Substructure and Coastal Protection Basic Design by Daryabandar
- Drainage System Design for Onshore Gas Plant by Abfan
- Accommodation Camps and Offices basic Design by RahShahr
- Basic Design for NIOC Operating Base by Daryabandar
- Field Measurement and Modeling for NIOC Operating Base by Darya Negar Pars
- Review and Approval of Basic Design for NIOC Operating Base by Alive Vof
- Following study is ongoing:
- 3D Seismic Data Processing & Interpretation
- Consultants: CADCAM and Paradigm
- Commencement Date: November 27, 2006
- Progress : 99.48%
2.Onshore Facilities
- Gas Plant Main Site Preparation EPC
- Contractors:
- Abad Rahan Pars
- Fater Kousaran Jonoob (The contract has been terminated)
- Karan Darya (Implementation of Coastal Protection as Additional Work)
- Overall Progress: 94.26%


- Accommodation Camps and Offices Site Preparation:
- Contractor: Abad Rahan Pars
- Commencement Date: December 4, 2007
- Progress: 88.48%


- Gas Plant Flood Protection Channel:
- Contractor: Abad Rahan Pars
- Commencement Date: December 4, 2007
- Progress: 19.09%
- Gas Plant Flare Substructure EPC
- Contractor: Karan Darya
- Commencement Date: December 11, 2007
- Progress: 28.69%


- Gas Plant EPC1, Tanks And Non-Industrial Buildings EPC Contract
- Contractor: NASR Consortium
- Commencement Date: May 14, 2008
- Progress: 3.38%
- Gas Plant, Liquid Processing And Utilities EPC Contract (EPC2)
- Issued TBE report and ongoing commercial bid evaluation for Onshore Gas Plant EPC2 tender
- Forecast award date of the contract will be mid September 2008
- Gas Plant, Gas Processing EPC Contract (EPC3)
- Ongoing technical bid evaluation for Onshore Gas Plant EPC3 tender
- Forecast award date of the contract will be late October 2008
- Gas Plant Long Lead Items
- Signed contract with OTC/Siemens for supply of Off Gas and Refrigerant Compressors as Gas Plant LLIs
- Concluded the tender for Nitrogen Generation Package
- Bid closing date for Manual and Shutdown Valves greater than 32"
- Ongoing tender evaluations for the rest
3. Offshore Facilities
- Wellhead Platform Jackets EPCI
- Contractor: ISOICO
- Commencement Date: January 8, 2007
- Progress: 59.25%
- Topsides and Ancillaries EPCI
- Contractor: IOEC
- Commencement Date: January 10, 2008
- Progress: 0.7%
- Sealines and SPM & Condensate Export Facilities EPCI
- Contractor: IOEC
- Commencement Date: October 15, 2007
- Progress: 16.41%
4. Wells
- Tendering and Management
- Signed the contracts for supply of drilling tubular, Wellhead & X-mas Tree, Down Hole Completion & Liner Hanger Equipment and drilling Jack-up Rig
- Held 17 tenders by Auxiliary Transaction Committee for urgent drilling needs
- Finalized tender for drilling Mud Line Suspension and Surface Wellhead contract
- Ongoing technical bid evaluation for drilling Integrated Technical Services
- Tender for materials to supply of drilling 26" conductor is being concluded
- Appraisal Well Drilling
- Start Appraisal Well drilling on June 26, 2008, drilled 2185m by end of July 2008
- Actual progress of operation up to end of July is 17.04% vs 19.97% plan
- 36'', 26" and 17 ½" sections drilled and completed
- Ongoing drilling on section 12 ¼"
- Supply of Materials, Equipment and Services
- Delivery of Tubular for PO No.1 to the warehouse in Kish by SUMITOMO
- Most of required materials for appraisal well are borrowed from POGC and PEDCO and all of them run in well up to this section successfully
- Received part of the FZE ordered materials to warehouse in Kish and some of the others finalized and scheduled for delivery
5. NIOC Operating Base
- NIOC Operating Base EPC:
- Issued TBE report and ongoing commercial bid evaluation
- Held tender for geophysical study of the step-like feature in the south of NIOC OPBS port
- Following up the NIOC Operating Base permissions from EPO & PSO
- Submission of technical and commercial clarifications to bidders
- Forecast award date of the contract will be in September 2008
|
|
|
 |
|