Our Projects South Pars Phase 12 Project Deliverables
|
|
| |
|
 |
|
|
|
1. Onshore Facilities
-
An integrated Gas Plant will be constructed in Tombak, 65 km west of Assaluyeh, to receive and treat 3 bscfd of the reservoir fluids coming from Offshore. The Gas Plant comprises the below facilities:
-
Reception of the three-phase fluid from the three 32” Sealines, through a common slug catcher followed by HP separators where a primary level of gas and liquid separation is achieved
-
Gas sweetening (H2S and partial removal of CO2)
-
Dehydration of the wet sweet gas
-
Dry gas dew pointing
-
Mercaptans removal
-
Compression of the treated dry gas for injection to the network
-
Stabilization of the untreated condensate
-
Desulphurization of the untreated stabilized condensate
-
Process water handling
-
Sulphur recovery and forming
-
All utilities (Power, Water, Air, N2, … )
Gas Plant has been planned to be executed through 3 separate EPC packages, each with following particulars:
-
Gas Plant EPC1 - Buildings/Tanks
-
Fire Fighting System
-
Condensate Storage and Export System
-
Chemical Storage/Diesel Storage
-
Relevant Roads and Paving
-
Relevant Technical Buildings
-
All non-technical Buildings with overall area of about 21000 m2 and including:
-
Gas Plant EPC2 - Liquid Processing/Utilities
-
Slug Catcher/HP Separators
-
Condensate Stabilization (3 Trains) + Backup
-
MEG Regeneration Unit/Sour Water Stripper
-
Flares/Blowdown/ Burn Pit System/Utilities and Offsite Drain System
-
Relevant Technical Buildings together with Central Control Building + Laboratory + Telecommunication Building/Relevant Roads and Paving
-
Power Generation/Emergency Power System/Steam Generation/Fuel Gas System
-
Instrument and Service Air System/Nitrogen Generation System
-
Sea Water Intake and Outfall/ Waste Effluent Disposal
-
Desalination/Water Polishing/Potable Water/ Cooling Water
-
Gas Plant EPC3 - Gas Processing
-
Six Gas Processing Trains including Gas Sweetening, Gas Dehydration, Gas Dew-Pointing and Gas Mercaptans Removal (Mol. Sieve)
-
Export Gas Compression
-
Sulphur Recovery and Tail Gas Treatment
-
Sulphur Granulation and Transit Storage
-
-
Relevant Technical and non-technical Buildings
-
Relevant Roads and Paving
-
Onshore Accommodation Camps and Offices
-
These facilities contain Petropars administrative offices and also residential camps for occupancy of 18000 persons at SPEEZ site no.2 area. Residential camps are including one camp for POGC personnel, one camp for PPL personnel, three camps for 3 Gas plant EPCs contractor's workers, two camps for non Iranian workers and three camps for Iranian and non Iranian managers
-
The Accommodation Camps have to be built by EPC1, EPC2 and EPC3 contractors respective to their SOW

- Gas Plant Flare Substructure EPC
- Project Elements
- Entrance and LP Flare area
- Main breakwater
- Length: 350m
- Width: 20m (Trunk) ,40m (Head)
- Western breakwater
- Length: 220m
- Width: 20m (Trunk) ,40m (Head)
- Eastern breakwater
- Length: 227m
- Width: 20m (Trunk) ,40m (Head)
- Gas Plant Long Lead Items:
- Totally 11 Long Lead Items for Gas Plant
- LLIs to be free issued to EPC Contractors
2. Offshore Facilities
-
-
Separation of free and condensed water from reservoir production in Free Water KO drums, two numbers on every platform each designed to handle 600 MMSCFD reservoir fluids
-
Oily water degassing & treatment prior to disposal to the sea
-
Export of the water saturated reservoir production to the onshore gas plant via three 32” sealines, one for each wellhead platform, operated in three-phase mode, i.e. gas, hydrocarbon condensate and condensed water.
-
Injection of MEG solution at the inlet of each sealine to inhibit both hydrate and corrosion.
-
Wellhead Platform Jackets
-
Topsides and Ancillaries
-
3 Identical Topside Wellhead Decks
-
3 sets of Topside Ancillaries (including Flare, Tripods, Supporting Decks and associated Bridges)
Sealines
3. Development Wells
4. NIOC Operating Base
|
|
|
 |
|